500 NORTH ROAD WORK
Submitted by City Engineer Bart Mumford
Heber City's contractor, Geneva Pipe, will soon begin
repair work on sections of sewer line in 500 North,
between 100 West and 300 West. The work will begin
Monday, January 7th, and is anticipated to continue for 6 to
8 weeks. Final road repaving will occur next spring when
temperatures allow. Due to the significant depth of the
pipe, the work must be done during the winter when
groundwater levels are low. Road closures along 500
North will be required, however, local traffic will usually
have access to their homes. The contractor will work to
minimize disruptions during the construction and
residents are requested to not park on the streets when
work is occurring nearby.
For specific information regarding the construction and
schedule, please contact Jared Wolfgramm with
Geneva Rock at 801-592-4570.
The City understands the inconvenience this causes
residents and will work to accommodate special needs
during the repair work.